Freeland Care Home

Our first job for PDR Construction at Freeland Care Home, This will eventually form a new extension to the existing care home. KCC are currently preparing for the floor slab after since doing the reduce dig totalling over 4000m3 carted off site by our friends at Earthline. We have now poured the foundations and are constructing the under slab drainage in preparation for the upper concrete slab.

External Works