Ardley, Oxfordshire, 13 Houses

Our latest project to start since the return back to work is 13 new houses for Harper Group.

We commenced on site on Monday 1st June and are currently doing the site strip and access road with soak away due to go in next week.

Our 1st phase of works is roughly 10 weeks before returning for the external works.

Progress continue's at speed on the Ardley project with first foundations dug and poured and the new soak away tank is already being installed.

Soak away crate now completed.

Week 4 finished and pot and beam going on along with incoming services.

Drainage runs going in. Plots are now up to block and beam height.