Quad 1 Floor Slab Poured.

  • Writer: John Cook
    John Cook
  • Apr 19, 2017
  • 1 min read

150mm ground floor slab is now in place and external Sheet Seal 226 DPM is installed to allow curtain walling to commence. This concludes our work to the structure and leaves only a small ammount of drainage and the external hard lanscape to complete.

 
 
 