Quad 1 Hard Landscaping Update

The South elevation is now almost complete with a little over 3 weeks to go we still have alot to do. The guys have really worked hard to get this far and the quality of work is excellent so hats off to them.

The permeable carpark is now complete as is the footpath running along side.

The swale is now being planted and starting to really take shape.

All efforts are now on the west and north sides which should be completed by close of play this week.

Work to the east and Pavillion building are hindered by other trades which need to get a move on.