Cobalt Building Harwell

Another development for SDC at Harwell, this project began early 2018 but was delayed when ground conditions were not as expected when possession was taken. Since then a full stabilisation has been carried out down to 3m deep prior to foundations being dug.

KCC came in after and dug all foundations and set over 70 sets of bolts in a little over a week.

KCC moved on drainage shortly after the foundation was completed and installed 5000 Aquacell Core crates in a hole 28 x 10 x 4m deep.

Project is now completed with the external works done. KCC did all preparation for surfacing along with the block paving.

KCC also prepared all the tree pits and and topsoiled all area's to receive planting.